The proposed Ballyglass Solar Array will comprise c.595 square metres of solar panels, located approximately 1km to the north-east of Ardnacrusha. The purpose of this website is to inform the local community about this proposed development. This will provide a significant contribution to achieving the country’s renewable energy targets and assist in reducing Ireland’s dependency on fossil fuels. The proposed development will generate direct and indirect local jobs and provide investment in the area through local authority rates / contributions and a community benefit fund will be made available to fund local initiatives as decided by the local community.

This proposal will be developed by Reeve Wave Ltd., an associate company of Enerco Energy Ltd. which is Irish-owned and based in Cork, with extensive experience in the design, construction and operation of Renewable Energy Developments throughout Ireland. 

For more information on the company, click here.

04/07/2022
Phase 1 Planning Application Lodged
25/08/2022
Phase 1 FI Request
07/12/2022
Phase 1 Response to FI
17/02/2023
Phase 1 Decision to Grant Permission
14/03/2023
Phase 1 Decision Appealed
18/07/2023
Phase 1 Appeal Decision Delayed
17/10/2023
Phase 1 Appeal Decision Delayed
21/11/2023
Phase 1 Decision to Grant
04/10/2024
Phase 2 Planning Application Lodged